KC Wright Building Hurricane Repairs & Structural Upgrade

SIZE OF PROJECT

350,000 SF

SECTOR
Commercial Office / Institutional
LOCATION
Fort Lauderdale, FL

Why It Matters

  • Recovery & Turnaround Project
  • Immediate Building Assessment & Weatherproofing Within 24 Hours of Storm
  • Mobilized Equipment & Materials Without Power or Readily Available Fuel
  • Completed $1.3 Million in Repairs Within 3 Week of Storm
  • Fast-Tracked $10 Million in New Glass & Structural Repairs

“As soon as the storm passed, we were called to this site as a special favor to the School Board. No one in the area had power. We were working 12 hour days, walking up and down 14 flights of stairs because the elevators weren’t working, and then going home at night to take cold showers in the dark. I’ll never forget it.”

-Mia Asmus Tunnicliff